The operation used a 8200 K-Mill with TruEdge inserts powered by a 6-3/4 inch OD mud motor to create a window behind the 9-5/8 inch casing, allowing for effective reservoir isolation.
Challenging Section Milling Operation in the Mediterranean Sea
Results:
• Successful project execution that exceeded customer expectations delivering a 60m barrier interface.
• Multiple technologies functioned as intended.
• Successful runs of an 8200 K-Mill with a 6-3/4 inch mud motor via a HWOU.
*Mark of Wellbore Integrity Solutions.